Working alongside main contractor JJ Rhatigan & Company, BJF Group’s MEP Residential Team has completed a new project as part of a £16m development in Hoxton, London.
The project, which took around 6 weeks, saw BJF Group complete all of the Mechanical elements and commissioning for 36 stylish 1,2 and 3 bed apartments and 3941m² of commercial office space.
The works included the installation of a mechanical plant room, heating and domestic pipework, 1st and 2nd fix bathrooms, commissioning HIU’s and plant, flushing and chlorination of heating and domestic pipework and rainwater pipes.
Paul Newstead, Senior Contracts Manager at JJ Rhatigan said:
“On behalf of JJ Rhatigan, I greatly appreciate the work BJF Group have put in to this project and your commitment to delivering a quality installation from start to finish. Please pass on our thanks to your teams, great effort from all involved”
Follow JJ Rhatigan:
Linkedin: JJ Rhatigan & Company
Twitter: @JJRhatigan
Instagram: @jj_rhatigan